|
It's
déjà vu. Whether you're involved in electrical design or installation,
you've
seen
this happen before: The lowest bid price supersedes quality ,
qualification, and
experience.
Unfortunately,
this scenario is taking place in the electrical maintenance sector as
well. The front office says money is tight and that the required yearly
electrical maintenance will be submitted for bid to all comers as well
as to your favored, knowledgeable company. This should be where the red
flag goes up. Whatever the initial "savings" gained, they
literally may go up in smoke.
Let
me cite an example (a true case history) provided by John Moore, a
former president of the InterNational Electrical Testing Association
(NETA) and a good friend of EC&M. A medium-sized food
processing plant originally built in the early 1950s had switch gear of
the same vintage. The plant engineer, who had been with the plant for
many years, was highly respected and very knowledgeable of his
electrical system. To keep the 40-year-old switch- gear at optimum
performance capability, he had the two main circuit breakers retrofitted
with solid-state tripping performance capability, and even built a
special room with filtered air around the switch- gear lineup.
The
plant engineer followed NFPA 70B recommendations for preventive
electrical maintenance and had the plant's switch- gear serviced by a
qualified service organization every two to three years. As a result of
these efforts, the plant had never suffered an in-service electrical
failure.
One
day, the "edict" came down from corporate: "We need to
cut costs; from now on, we go out to bid, and the lowest bid gets the
order." The plant engineer reluctantly put aside the longtime
relation- ships and trust he had built over the years with two qualified
testing companies and went out to open bid.
To
the plant engineer's surprise, the low bidder turned out to be a local
contractor that he was familiar with. He had no knowledge that this firm
even did field
|
|
John
A. DeDad,
Editor-in-Chief

maintenance
testing work. All he knew was that it was a reputable firm that also
manufactured some electrical products. Nevertheless, the company's
bid was low, and the plant stood to save $1500.
As
it had in previous years, the scheduled
weekend came for the utility shut- down. However, this shutdown seemed a
little different. The contractor didn't insist on a tailgate safety
meeting prior to the shutdown to make sure everyone under- stood the
hazards involved, how to use personnel protective equipment, and what
procedures to use to ensure that the job would be conducted safely,
accurately, and efficiently. In fact, the low bidder's people already
were wandering about, removing panels from the back of the switch gear
and exposing live bus bars way ahead of the scheduled utility shutdown.
A worker began vacuuming the open and energized switch gear and, after a
few hours, decided to take a smoke break, leaving his vacuum behind the
open switch gear.
The
worker had not yet left the room when the explosion occurred. The
concussion blew out 75 window panes at the front of the building. In a
matter of minutes, the 3000A switch gear was reduced to a useless mass
of molten metal and debris. Miraculously, no one was injured. Thanks to
the vacuumer's smoke break, no one was behind the switch gear.
When
the thick black smoke finally cleared and the fire trucks left, the
plant engineer was left with many unanswered questions.
~
Why
wasn't a previously thought out method or procedure used?
~
Why
wasn't a tailgate safety meeting held?
~
Why
weren't the contractor's workers equipped with protective
equipment?
|
|
~ Why
was the work performed live when all the contractor had to do was wait
for the scheduled utility outage?
The
resultant cost of this "low" bid was astronomical. The
switchgear replacement alone was $175,000, not to mention the building
concussion and smoke damage, the loss of production, and lost wages. And
after several years, the cost of litigation is still adding up.
The
old cliché "You get what you pay for" clearly does not go far
enough in cases such as this. The true cost of this low bid was more
than 50 times the bid price, not counting the extra worry, concern, and
aggravation. Fortunately, no one paid the ultimate price with his or her
life. Unfortunately, many do on other such maintenance testing jobs.
What's
my point in citing this example? As John Moore succinctly points out,
"Selecting a qualified service organization to maintain your
electrical systems might just be the most critical element of electrical
maintenance."
NETA
suggests the following minimum criteria for making such a
selection before considering price:
~
Is
electrical field service the regular business of the proposed
contractor, or is it a company simply trying to increase sagging profits
by entering into areas in which it isn't proficient?
~
Has
the company been in field service business for at least two years, and
is it equipped for the job?
~
Does
the contractor have a written safety plan? Ask to see it. Check the
contractor's OSHA 200 logs. Ask what the company's OSHA incident rate
is.
~ Are
the contractor's field technicians certified by NETA or NICET?
In
other words, check the proposed con- tractor out before sending the
purchase order; you could be committing your plant to the most expensive
"cheap" job it's ever had.

Prior
Article |